Development Project of South Yaran Oil Field
Main Objectives
Daily production of some 25,000 barrels of crude oil
Contract Type
From internal resources of NIOC
Geographical Location
It is 130 kilometers to the west of Ahwaz, in Iran-Iraq borderline (in Talaeiyeh area), i.e. in the southwest of the county.
Implementation Period
18 months (according to the approval of NIOC Board of Directors for production from the field). Date of completion: January 20, 2015
48 months (according to the approval of NIOC Board of Directors, with installation of facilities). Date of completion: July 21, 2017